Dubai Airports (DXB) said the northern runway will reopen as per schedule on June 22, as renovation work crosses the half-way mark.
In a statement, Dubai Airports said the renovation project will see "the resurfacing of the 4.5 km-long runway, strengthening of the wider runway strip, as well as reinforcing the paving on key taxiway entries and exits, and repairing of the drainage infrastructure".
Aeronautical ground lighting, navigational aids and meteorological equipment are also being replaced, and a navigation aids substation is being relocated.
More than 1,000 vehicles and 3,000 people have been working on-site at DXB since work began on May 9.
The primary objective of the project is to "enhance the safety, operational efficiency, and capacity at DXB".
During the 45-day closure, more than 1,000 flights from several international carriers, including flydubai, SpiceJet, Indigo, Gulf Air, Air India Express and Qatar Airways were shifted to the Dubai World Central (DWC).

UAE orders arrest of 10 for publishing misleading online content
Abu Dhabi Police arrest 45 for filming incident sites, sharing rumours
UAE Cyber Security Council warns against 'Wiper' malware
Dubai Police crack down on noisy cars, illegal modifications
UAE President, Ethiopian PM discuss boosting economic, development ties
UAE air forces respond to more missile threats on Friday
UAE air defences intercept 7 ballistic missiles and 27 drones on Friday
GCAA reveal "strategic resumption" as 1.4 million passengers use UAE airports in March