Intensive maintenance works have been carried out on the Dubai Metro network during the national disinfection drive.
Officials at Dubai's Roads and Transport Authority (RTA) took advantage of the lockdown period in April to complete the work at a much quicker rate than usual.
The additional hours helped them finish the bulk of the project well ahead of the initial schedule, with the completion rate hitting 180 per cent in certain sections.
The work mainly focused on rail tracks, tunnels and other periodic as well as essential maintenance activities.
.@rta_dubai carries intensive rail maintenance during national disinfection programhttps://t.co/btME5t4N9I pic.twitter.com/5CKG2a5ra9
— Dubai Media Office (@DXBMediaOffice) June 21, 2020

UAE launches aid mission for hurricane-hit Caribbean nations
New paid parking zones introduced in Dubai
H.H. Sheikh Khaled holds talks with South Korean President
UAE fuel prices to drop in November
Abu Dhabi Crown Prince arrives in South Korea for APEC Forum
UAE condemns attacks on civilians in Sudan's El Fasher
Arab Parliament commends UAE’s humanitarian efforts in Gaza
UAE aid ship reaches Egypt with vital supplies for Gaza