A AED 2.5 billion project to drain rainwater in areas around Expo 2020 Dubai is on track for completion by September next year.
Around 65 per cent of the deep tunnel network is now ready.
It’s the largest of its kind in the Middle East and is designed to serve an area of 490 km.
Construction work is being carried out in various shifts for 24 hours every day, with nearly four million man-hours already invested in the project.
Dawoud Al Hajri, Director General of Dubai Municipality, said: "The project will have a major impact in developing the groundwater drainage infrastructure for Al Maktoum City, the Expo area and the Airport City, and will remain in service for a century."

Dubai fully prepared for massive New Year’s Eve celebrations
UAE fuel prices to drop in January
62-minute fireworks, 6,500 drones to light up Sheikh Zayed Festival
Dubai NYE: Road closures, traffic plan announced
UAE celebrates its workforce in New Year festivities
RTA lists main firework displays for New Year's Eve
UAE President discusses cooperation with Pakistani PM
Dubai confirms free parking on New Year’s Day