Intensive maintenance works have been carried out on the Dubai Metro network during the national disinfection drive.
Officials at Dubai's Roads and Transport Authority (RTA) took advantage of the lockdown period in April to complete the work at a much quicker rate than usual.
The additional hours helped them finish the bulk of the project well ahead of the initial schedule, with the completion rate hitting 180 per cent in certain sections.
The work mainly focused on rail tracks, tunnels and other periodic as well as essential maintenance activities.
.@rta_dubai carries intensive rail maintenance during national disinfection programhttps://t.co/btME5t4N9I pic.twitter.com/5CKG2a5ra9
— Dubai Media Office (@DXBMediaOffice) June 21, 2020

UAE condemns hostile Iranian attack targeting Qatari vessel
UAE certifies world's first commercial air taxi vertiport
Ajman unveils AED 1.8 billion urban development roadmap
H.H. Sheikh Hamdan honours government entities for digital transformation
H.H. Sheikh Mohammed to honour 'most beautiful Quranic voices in the world'
Abu Dhabi to establish specialised court for human trafficking crimes
Dubai expands support for aspiring Arab podcasters
Mohammed Saeed appointed National Media Authority's Secretary-General