The Roads and Transport Authority (RTA) has completed all phases of the Al Khail Road Development Project, which included the construction of five bridges stretching 3,300 metres and road widening across 6,820 metres.
These improvements are spread across seven locations along Al Khail Road: Al Jaddaf, Business Bay, Zabeel, Meydan, Al Quoz 1, Ghadeer Al Tair, and Jumeirah Village Circle.
The project serves 1.5 million residents, cutting travel time by 30 per cent and boosting the capacity of intersections and bridges to handle approximately 19,600 vehicles per hour.
These enhancements not only improve traffic flow but also eliminate congestion at interchanges.
To expedite construction, the RTA adopted an innovative strategy, reducing the project timeline from 18 months to just 9 months by partnering with multiple contractors.
This accelerated effort saw a daily workforce of 5,000 engineers and workers logging a remarkable six million work hours, utilizing 650 pieces of machinery.
The Al Khail Road Development is a crucial component of Dubai's road network, linking major routes like Sheikh Zayed Road and Sheikh Mohammed bin Zayed Road.
This vital arterial road features five lanes in each direction, expanding to over six lanes in certain areas, further enhancing the connectivity and efficiency of Dubai's transport system.

UAE expresses solidarity with Greece over death of two pilots in plane crash
H.H. Sheikh Mohammed pays tribute to UAE President in personal message
UAE joins 7 other countries in rejecting displacement of Palestinians from Gaza
Five UAE aid convoys enter Gaza carrying 533 tonnes of supplies
UAE search and rescue team begins field operations in flood-hit Nepal
Dubai Police completes 104 technology projects in a year
UAE leaders meet with King of Bahrain to discuss regional issues
New RTA development at Al Qiyadah Intersection cuts traffic by 15 per cent